In PMI’s (Project Management Institute’s) Project Management Body of Knowledge or PMBOK – which is the bible of project management, there are 9 knowledge areas discussed– Integration, Scope, Time, Cost, Quality, Human Resources, Communications, Risk, and Procurement. Anyone who has studied for their PMP certification knows these well – ad nauseum even, and knows that the PMBOK discusses these with equal weight. Indeed, PMI loves all of her knowledge area “children” equally, but out in the real world there is one that I believe deserves your extra undivided attention and that is scope.
Most people who have worked on a project in any capacity are familiar with the notion that projects are controlled constantly by what’s known as the triple constraint – time, cost, and scope. You can control any 2 of those factors and the third one will be defined for you. Never do projects begin with a fixed amount of time or budget and an organization saying “Gee, I wonder what work we could go do with all this time and money?” Projects begin because there is a specific need to address, problem to solve, or opportunity to realize – i.e. scope. It must be the first thing defined and boundarized in a well formed scope statement. After that you determine the amount of time and cost to adequately deliver the scope of work of the project. While I will concede that neglecting schedule, budget, quality, communications, human resource issues or risk management can certainly hurt a project badly, neglecting scope management will kill a project. This is because it is the very essence of what defines success for the project. It is the “what you are doing” on the project. You can work very fast and inexpensively, but if you have worked on the wrong things, you will not be declared successful.
From a public relations perspective, scope can be one of the areas that generates the greatest potential for confusion so project managers should begin communicating what is in and out of scope early and often to wide audiences of stakeholders – within and beyond the project team. One of the worst morale killers on a project is when a high level stakeholder says late in the game “but I thought I was getting ‘X’ “. The project charter and high level scope statement documents serve as good tools to aid in these types of presentations. Once the detailed baseline scope statement is developed, it should be formally approved by the project sponsor, communicated widely, and constantly controlled. To control the scope, we advocate adopting a form for use in capturing scope change requests from the outset and setting up a committee of sponsoring stakeholders (not including the project manager) responsible for approving changes. Change requestors should document the change and presumed benefits, and the implementation team should have a chance to document the impact to the current project schedule and budget. This package is then presented to the change committee for decision. The project manager must communicate the final decision to all stakeholders and factor the impact back into the project plan. This allows sponsors to remain in control of the resources, and keeps the project manager from being the “bad guy” if the decision is No. It also provides a mechanism for protecting the team against taking on extra work without the benefit of the time or extra resources to accomplish it.
So it behooves project managers to seek out opportunities to communicate scope as often as possible. Let’s review some of the typical venues and aids for scope communications:
| Venue | Audience | Communication Aids |
| Charter Review Meeting | General interested stakeholder | Project Charter |
| Scope Statement Development Meeting | Project Team | Scope Statement |
| WBS Development Meeting | Project Team | WBS |
| Estimation Meeting | Project Team | WBS |
| Project Kickoff Meeting | Project team | Project Charter; Scope Statement; Roles & Responsibility Matrix; Project Org Chart |
| Executive Sponsor meetings | Executive sponsors | Scope Statement; Project Schedule; Roles & Responsibility Matrix; Project Org Chart; Change Requests |
| Stakeholder Meetings | General interested stakeholder | Project Schedule; Roles & Responsibility Matrix; Project Org Chart; Change Requests |
| Change Control Meetings | Change Board | Change Requests; Project Schedule |
| Project Team Meetings | Project Team | Scope Statement; WBS; Project Schedule; Change Requests |
Keeping all interested parties aware from the outset of the approved scope, and any subsequent changes, so that there are no surprises downstream is in the best interests of the project team.
3 Comments to 'Scope is King – The Public Relations of Project Management Management Part 3'
November 19, 2009
The Communication Table at the end of the article is great (as is the whole article).
I am interested in publishing this article on PM Hut, please either email me or contact me through the “Contact Us” form on the PM Hut site in case you’re OK with this.
April 25, 2011
Just found your article on scope as I am studying for my PMP exam. The article is helpful. I am having a hard time understanding when to create a new project vs. perform integrated change control (ie. take it to the ccb). Here’s an example of a question that I got wrong on a mock exam:
You are the Project Manager for XYZ project. The scope of the project has been completed. You receive a request for a new module to be developed as part of this project. What should you do next?
A. You should approach the Project sponsor and ask her for a new module to be developed as part of this project.
B. You should approach the Senior Management and ask them for a new module to be developed as part of this project.
C. You should send the request to Change Control Board for approval.
D. Since the project scope is completed you should inform the customer that this change cannot be done as part of the project.
I guessed C, but the correct answer is D. Even if the scope is “completed” – I thought the scope could be modified (change is inevitable!) via change controls set forth. Can you shed some insight as to the differences between processing changes through change control vs. starting new projects?
Thanks in advance!
May 4, 2011
Well this is a tricky area to be sure, and you are discovering as we all have how devious the PMP exam questions can be. There are certain situations (and practice exam questions I’ve seen) where the correct answer would indeed have been to assess the change, document it, and present to the sponsor for consideration, or the CCB – thus incorporating problem solving and integrated change control which are 2 principles PMI loves and you can nearly always bet on with a test question. I think the key here centers around where you are in the spectrum of the project. Once deliverables, and the final scope of the project have been accepted, then you’re done and that project is finished and ready to be closed. If the customer wants more, then it’s a new project. With the wording “the scope of the project has been completed”, I guess you are supposed to surmise that you are at that final point in the project.
Hang in there, and best of luck with your exam.
Leave a comment